Larsen seeks compensation in the total amount of USD 20,039,525 for contract losses, loss of tangible property, payment or relief to others and financial losses..
Samsung要求赔偿总额为78,791,431美元的合同损失、利息损失和有形资产损失。
Samsung seeks compensation in the total amount of US$78,791,431 for contract losses, loss of interest and loss of tangible assets.
Dodsal seeks compensation for contract losses allegedly incurred in connection with the Saddam Oil Field Development Project(DM 6,146,018) and the Anfal Gas Field Development Project(US$180,691).
小组同意Strabag的说法,即第53号索赔没有与目前提出的合同损失索赔重叠。
The Panel agrees with Strabag' s assertion that Claim No. 53does not overlap with the current claim for contract losses.
Chiyoda seeks compensation in the amount of USD 8,610(JPY 1,242,000) for contract losses allegedly incurred in relation to materials supplied to the Basrah Refinery project.
在原来的"E"类索赔表中,Anice要求赔偿未付款的发票的合同损失1,299,111美元。
In the original" E" claim form,Anice sought compensation in the amount of USD 1,299,111 for contract lossesfor unpaid invoices.
NCC要求赔偿的合同损失涉及与ABV订立的一项合同。
The contract losses for which NCC seeks compensation arise out of a contract entered into by ABV.
因此,小组考虑了金额为4,043,675美元的下列合同损失、利润损失、和有形财产损失:.
The Panel therefore considered the amount of USD 4,043,675 for contract losses, loss of profits and loss of tangible property, as follows.
Three of the projects mentioned by Bojoplast were the subject of contract loss claims by Industrogradnja: P-195, P-500 and P-196.
小组认为,DeutzService所称的合同损失完全涉及1990年5月2日之前完成的工作。
The Panel finds that the contract losses alleged by Deutz Service relate entirely to work that was performed prior to 2 May 1990.
小组建议对于由火警系统合同所产生的合同损失赔偿4,586德国马克(2,935美元)。
The Panel recommends compensation in the amount of DEM 4,586(USD 2,935)in respect of the contract losses arising out of the contracts for fire alarm systems.
The Panel finds that the contract losses alleged by Bangladesh Consortium for this employer relate entirely to work that was performed prior to 2 May 1990.
小组认定,Krupp所称的合同损失完全涉及1990年5月2日之前所作工作。
The Panel finds that the contract losses alleged by Krupp relate entirely to work that was performed prior to 2 May 1990.
尽管如此,但实际情况是,Samsung公司索赔的合同损失完全涉及1990年5月2日之前完成的作业。
That said, it is the case that the contract losses for which Samsung claims are wholly in respect of work that was performed prior to 2 May 1990.
小组发现,中国有色指称的合同损失完全涉及1990年5月2日以前进行的工程。
The Panel finds that the contract losses alleged by China Nonferrous relate entirely to work that was performed prior to 2 May 1990.
小组认为,Salzgitter提到的合同损失完全与1990年5月2日之前完成的工程有关。
Analysis and valuation The Panel finds that the contract losses stated by Salzgitter relate entirely to work that was performed prior to 2 May 1990.
本批的合同损失索赔为一件,没有提出任何新的法律问题或核实和估价问题。
The one claim for loss of contract in this instalment did not raise any new legal or verification and valuation issues.
根据这种推理,小组认为KOSC的合同损失为11,489科威特第纳尔,因此建议赔付这一金额。
Applying this reasoning, the Panel finds KOSC' s contract losses to be valued at KWD 11,489 and recommends the payment of compensation in this amount.
然而,专员小组认为Lewis的合同损失不是由伊拉克入侵和占领科威特直接造成的。
However, the Panel finds that Lewis's contract loss was not directly caused by Iraq's invasion and occupation of Kuwait.
中文
Bahasa indonesia
日本語
عربى
Български
বাংলা
Český
Dansk
Deutsch
Ελληνικά
Español
Suomi
Français
עִברִית
हिंदी
Hrvatski
Magyar
Italiano
Қазақ
한국어
മലയാളം
मराठी
Bahasa malay
Nederlands
Norsk
Polski
Português
Română
Русский
Slovenský
Slovenski
Српски
Svenska
தமிழ்
తెలుగు
ไทย
Tagalog
Turkce
Українська
اردو
Tiếng việt