Examples of using Task usage in English and their translations into Romanian
{-}
-
Colloquial
-
Official
-
Medicine
-
Ecclesiastic
-
Ecclesiastic
-
Computer
-
Programming
You add these fields to the Task Usage view.
You add this field to the Task Usage view and use it to filter and review assignments to contractors.
This field is available only in the Task Usage view.
Example In the Task Usage view, you want to see only assignment rows for assignments that have more than 80 hours of work.
These fields can be displayed in the timephased part of the Task Usage view.
To group assignments,select the Task Usage or Resource Usage view.
In addition to the timephased SPI,you can show total SPI for tasks in the sheet portion of the Task Usage view.
Add the Baseline Cost field to the timesheet portion of the Task Usage view to display baseline cost information.
If you had set the Fixed Cost Accrual field to Start or End, you would see the full $100 either at the beginning orend of the time period in the Task Usage view.
Add the Assignment field to the sheet portion of the Task Usage view when you want to display whether the field is an assignment row.
You save an interim plan and include the interim plan's start date in the Start1 field, andthen add that to the Task Usage view as well.
Best Uses Add the SPI field to the timephased portion of the Task Usage view to display or filter for the ratio of work performed to work scheduled.
If you want to see the timephased ACWP as of Tuesday, you enter Tuesday's date as the status date, andthen review the ACWP for the task in the Task Usage view.
The SPI is now 1.2,which is displayed for both Tuesday and Wednesday in the Task Usage view, indicating that you're now ahead of schedule.
Reviewing the field in the Task Usage view with the timescale set to days, you see that the SPI for Monday is 0.8 or 80 percent, indicating that the task is behind schedule.
These reports are based on the timephased data,similar to the data found in the Task Usage and Resource Usage views.
They can be displayed in the sheet portion of the Task Usage and Resource Usage views and at the bottom of the Task Form and Resource Form views.
Click Roll down unless manually entered if the contents of this custom field are to be distributed across assignments,for example, in the Task Usage view or Resource Usage view.
By reviewing the timephased Actual Work Protected field for the task in the Task Usage view, you can see that over the past two weeks, collectively they have worked a total of 80 hours.
If you want to see the timephased ACWP as of Tuesday, you enter Tuesday's date as the status date, andthen review the ACWP for the assignment on either the Task Usage or Resource Usage view.
Best Uses Add the Overtime Work field to the timephased portion of the Task Usage view to review overtime scheduled for a task for each period of time.
You add this field to the Task Usage view and use it to see resources grouped according to the organizational breakdown structure and to obtain summarized information based on this structure.
To see overall baseline budget work information for work ormaterial resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to the Task Usage or Resource Usage view.
In the timephased portion of the Task Usage view, you see that there are 8 hours of regular work scheduled across each of 4 days for a total of 32 hours of scheduled regular time.
Best Uses Add the TeamStatus Pending field to the sheet portion of the Task Usage or Resource Usage view to track the assignments that you still need progress information for.
In the Task Usage view, you show both the Baseline Budget Work and Budget Work fields in the timesheet portion of the view to analyze your work budget variances and determine whether you're on track or need to make any adjustments.
Best Uses Add the Actual Work field to the timephased portion of the Task Usage view to review or edit information on actual work for assignments on specific tasks over a period of time.
As overtime work is scheduled in the sheet portion of the Task Usage or Resource Usage view for the resource's various assignments, Microsoft Office Project rolls up these overtime work hours and enters the total overtime work for the resource into this field.
Best Uses Add one of the Baseline1-10 Cost assignment fields to the timephased portion of the Task Usage or Resource Usage view when you have saved more than one baseline and you want to analyze timephased baseline costs for assignments.
By using the timephased views in Project 2007(the Task Usage view and the Resource Usage view), you can change the timescale and update actual data at the level of granularity you need.