Exemple de utilizare a Office project calculates în Engleză și traducerile lor în Română
{-}
-
Colloquial
-
Official
-
Medicine
-
Ecclesiastic
-
Ecclesiastic
-
Computer
-
Programming
Microsoft Office Project calculates that the actual overtime cost so far is $180.
As progress(percentage of completion or actual work) is reported on the task,Microsoft Office Project calculates ACWP.
How Calculated Microsoft Office Project calculates regular work for a resource as the sum of all regular work for all assigned tasks.
After the resource begins work on the assignment and reports actual work,Microsoft Office Project calculates the remaining cost as follows.
As progress(percentage of completion or actual work) is reported by the resource on various tasks,Microsoft Office Project calculates ACWP.
Once actual overtime work is reported on this assignment,Microsoft Office Project calculates Remaining Overtime Work according to the following formula.
If any actual overtime work is reported by the resource assigned to the task,Microsoft Office Project calculates the actual overtime cost.
Once a resource begins work on the task and reports actual overtime work,Microsoft Office Project calculates the remaining overtime work and then calculates the remaining overtime cost as follows.
If any actual overtime work is reported by the assigned resource for any task,Microsoft Office Project calculates the actual overtime cost.
Once a resource begins work on the task and reports actual overtime work,Microsoft Office Project calculates the remaining overtime work for all assigned resources on the task.
Once the assigned resources begin work on the task and report actual work,Microsoft Office Project calculates the remaining cost as follows.
When you enter scheduled overtime work in the sheet portion of the Task Usage or Resource Usage view for the assignment,Microsoft Office Project calculates and distributes the resource's scheduled overtime work across the appropriate period of time and enters the numbers in the timephased fields.
As progress(percentage of completion or actual work) is reported on the task,Microsoft Office Project calculates the actual cost of work performed(ACWP).
Microsoft Office Project 2007 calculates variances by subtracting baseline values from the current estimated values in your schedule.
By default, Microsoft Office Project automatically calculates actual costs according to the actual work accumulated or material consumed on tasks.
After you begin tracking actual values, Office Project 2007 calculates the current estimated values(scheduled values) by adding the actual values, for work completed, to the baseline values for the work that remains.
Although Office Project 2007 calculates variances for several project measurements, these numbers are not enough information to help you determine the best use of your time.
Review cost totals to verify the totals that Microsoft Office Project 2007 calculated, based on cost information that you entered.
How Calculated Microsoft Office Project assigns the current date to this field based on the current date set in Microsoft Windows.