Examples of using Completed week in English and their translations into German
{-}
-
Colloquial
-
Official
-
Ecclesiastic
-
Medicine
-
Financial
-
Ecclesiastic
-
Political
-
Computer
-
Programming
-
Official/political
-
Political
Gestational age below 24 or over 33 completed weeks.
In other respects,Moore will assume liability in case of a delivery delay for each completed week of delay within the scope of a lump-sum compensation for default to the extent of 0.5% of the value of the goods delivered, yet at most 5% of the value of the goods delivered.
If we are in default and the Purchaser consequently suffers a damage/loss, our liability in cases of ordinarynegligence shall be limited to 0.5% per completed week of default, but in total to max.
Otherwise- in case of a delay in delivery we are to be blamed for- the customer can assert a claim for each completed week of the delay at a lump sum amounting to 3 percent of the value of the delivery, however, the maximum sum cannot be more than 15 percent of the value of the delivery.
Should delivery be delayed and we, our lawful representatives, or our vicarious agents have acted with ordinary negligence, our liability is limited to a maximum of0.5% of the contract value of the delayed goods per completed week of delay.
During the peak season the minimumstay is 7 nights requested and completed weeks it is possible to 9, 10, 11, 12.
In the case of supply delays,the Customer can demand damages for every completed week of the delay in the amount of 0.5%, provided he can prove that he has suffered damages as a result of this, but he may not demand more than 5% of the price for that part of the deliveries which could not expediently be taken into operation as a result of the delay.
Without prejudice to any further claims or rights HERION we shall be entitled to demand a contractualpenalty to the amount of 0.5% of the delivery value for each completed week, although not exceeding 5% of the delivery value.
If claims for damages are to be granted due to delay or in place of the deliverythen compensation is to be paid for every completed week of delay and this is to amount to 0.5 percent, but in total a maximum of five percent of the net price for that part of the delivery, which could not be placed in operation for its intended purpose, unless the buyer can show the occurrence of higher damages.
Should the Manufacturer establish that he cannot affect punctual delivery and the Purchasing Party can prove that this has given rise to damages,the Manufacturer is liable to pay compensation: for every completed week of non-delivery, this amounts to 0.5%, but no more than 15% max.
In case of slight negligence on our part, our liability for proven damagecaused by the delay is limited to a compensation for every completed week of the delay from 0.5%, however, to a maximum of 5% of the price for the part of the delivery that due to the delay could not be commissioned for the intended purpose.
If we default in delivery for reasons for which we are responsible, the customer is entitled from the fourthweek on to demand a flat-rate sum of compensation for each completed week amounting to 3% of the value of the delivery items up to a maximum total of 10% of delivery value.
Where delay in performance can be shown to have occurred solely through the fault of Seller,Buyer may claim for each completed week of delay an indemnity of at most one half of one per cent, a total of no more than 5%, however, of the value of that part of the goods to be delivered which cannot be used on account of Seller? s failure to deliver an essential part thereof, provided the Buyer has suffered a damage to the aforesaid extent.
In the event that we should be liable for the non-compliance with bindingly confirmed deadlines anddates, the buyer shall be entitled to late performance compensation in the amount of 0.5% for each completed week of default, however, only to a maximum of 5% of the invoice amount for the goods and services affected by the delay.
A delay in fulfillment through the sole fault of the sellerentitles the buyer to claim a contractual penalty, for every completed week of delay, of at most 0.5%, altogether not more than 5% of the value of that part of the total delivery at issue, if in consequence of the late delivery an essential part cannot be used, insofar as the buyer has accrued damages to that amount.
Provided that the Contractor is responsible for the noncompliance of bindingly agreed deadlines and dates or if he is in delayCustomer shall be entitled to a delay compensation amounting to 0.5% for every completed week of the delay; in total, however, a maximum of 5% of the invoice value of the supplies and performances affected by the delay.
We are entitled to a flat ratedamage compensation of 0.5% of the value of the delivery per completed week of the delayed delivery by retaining all additional rights, however, at a maximum of 10%;
In the event of default,the client shall be entitled to default compensation of 0.5% for each completed week of the delay, but in total up to 5% of the invoice value of the service affected by the delay.
In cases where Cool Italia is responsible for failing to meet binding dates and deadlines or is in default, the Purchaser is entitledto compensation for delayed completion at a rate of 1⁄2% for each completed week of the delay but the overall amount must not exceed 5% of the value of the invoice for the deliveries and services affected by the delay.
Should EMH be responsible for a delay in delivery, the Purchaser- if he canestablish credibly that a loss occurred from such a delay- may claim compensation of 0.5% for every completed week of delay but in no event shall the aggregate of such compensation exceed a total of 5% of the price of that part of the delivery which, because of the delay, could not be put to the intended use.
Any delay in delivery of more than two weeks verifiably caused by our gross negligence or intentional action shall entitle the orderer toclaim a maximum contractual penalty of 0.5% for each completed week of delay up to a maximum of 5% of the value of that portion of the relevant overall delivery which cannot be used as a result of the untimely delivery of a significant portion, provided the orderer has incurred damage in this amount.
In the last complete week;
Weekly prices apply for complete weeks from Sat-Sat.
The penalty is 1% of thepartial service delivery/ service scope for each complete week of delivery and service delay.
Much money, but also a complete week, which we needed for the cleaning and the renewed validation, cost us not only correctly.
Such compensation amounts to 0.5% for each complete week of delay, amounting to a total of no more than 5% of the price for the part of delivery and service that, due to the delay, could not be put into appropriate operation.
Otherwise, in cases of delayed delivery,we shall be liable to pay compensation for each complete week of delay within the scope of a flat-rate delay penalty amounting to 0.5% of the delivery value per week, but with maximum liability of 5% of the delivery value.
In the event of culpable delay in delivery our liability islimited to a lump-sum amount of damages of 0.5% per complete week, the maximum amount being 5% of the order value of the late delivery.
Otherwise, in the event of a delivery delay attributable to us, the Buyer may claim liquidateddamages to the amount of 3% of the delivery value for each complete week of delay, limited, however, to a maximum of 15% of the delivery value.
Inasmuch as we are responsible for the failure to observe bindingly agreed deadlines and timetables, or if we arelate in performance, the purchaser may claim compensation for delay amounting to one half of one percent for every complete week of delay, not, however, exceeding 5% of the invoice value of the delayed deliveries or performances.