(1) Development and validation phase.
Special Report No 7/2009- The management of the Galileo programme's development and validation phase.
A development and validation phase, running from 2002 to 2005;
(a) activities relating to the completion of the development and validation phase of the Galileo programme.
Information note of the European Court of Auditors concerning SpecialReport No 7/2009 on the management of the Galileo programme's development and validation phase.
Activity(ies): Development and validation phase of the Galileo programme.
Printed in Belgium Special Report No 7/2009-The management of the Galileo programme's development and validation phase.
The management of the development and validation phase was inadequate.
A development and validation phase which runs from 2002 to 2005 and covers the development of the satellites and the system's ground components, as well as validation in orbit.
The Court concluded that management of the development and validation phase was inadequate.
The development and validation phase would now run until early 2009,and deployment would take place in 2009 and 2010(a three-year shift with regard to the initial timetable).
The Court concluded that management of the development and validation phase was inadequate.
The development and validation phase was to be managed by the GJU, a dedicated structure set up by the Commission and the ESA after approval by the Council of the European Union and the ESA Council.
Closing down the GJU before the end of the development and validation phase underminedits authority60.
In order to manage the development and validation phase of the Galileo programme, the European Commission and the ESA set up a dedicated structure, the Galileo Joint Undertaking(GJU), which operated from September 2003 until the end of 2006.
This report addresses the period during which the Galileo Joint Undertaking(GJU) managed the development and validation phase, focusing in particular on its mandate, the process of setting it up and the management of its tasks.
The development and validation phase did not start until May 2003, 29 months later than planned(see paragraph 15). according to esa calculations, confirmed by the gJu, some 142 million euro in extra costs can be attributed to this delay43.
The audit addressed the period during which the GJU managed the development and validation phase, focusing in particular on its mandate, the process of setting it up and the management of its tasks.
The gJuŐs task of supervising technological development activities was seriously constrained by governance issues, an incomplete budget,delays and the industrial organisation of the development and validation phase.
Galileo programme's development and validation phase: special report- Council conclusions.
He went on to say that,“While keenly aware of the economic, industrial and strategic importance of satellite navigation, our Member States failed to reach an agreement,thereby delaying the start of the project's development and validation phase.”.
The Council takes note of the Court of Auditors Special Report No7/2009 on"The management of the Galileo programme's development and validation phase" concerning the European Union's involvement in satellite navigation in the period 2003-2006.
A development and validation phase, which was initially intended to run from 2002 to 2005and includes the development of the system's satellites and earth components as well as validation in orbit;
Technological development has been set back five years. as at the end of 2008,no operational satellites have been launched and cost estimates for the development and validation phase have almost doubled from 1,1 to 2,1 billion euro.
The audit addressed the period during which the gJu managed the development and validation phase(september 2003 Đ december 2006), focusing in particular on its mandate, the process of setting it up and the management of its tasks. audit work was performed during 2007 and 2008.
The GALILEO Joint Undertaking(GJU)- a PPP body setup in 2003 and scrapped in 2006- was given the task of supervising GALILEO's technological development activities but, according to the European Court of Auditors, the GJU"was seriously constrained by governance issues, an incomplete budget,delays and the industrial organisation of the development and validation phase".
The current schedule38 has the development and validation phase terminating in 2010 Đ five years late. according to the cost estimates produced by the esa in July 200839, development and validation will cost 1 billion euro more than the initial budget of 1,1 billion euro(see Table 3).
The timetable for the next phases of the galileo programme wasestablished as follows(see also Table 1):(a) the development and validation phase would run from 2001 to 2005;(b) the deployment phase would run from 2006 to 2007;(c) the commercial operation phase would start in 2008.
A development and validation phase comprising the construction and launch of the first satellites, the establishment of the first ground-based infrastructures and all the work and operations making it possible to validate the system in orbit, funded by the Community and the European Space Agency;
(9) The Galileo programmeincludes a definition phase which is complete, a development and validation phase due for completion in 2013, a deployment phase which was launched in 2008 and is due for completion in 2020 and an exploitation phase which should be launched progressively from 2014/15 for a fully operational system in 2020.