Exemple de utilizare a Earned value în Engleză și traducerile lor în Română
{-}
-
Colloquial
-
Official
-
Medicine
-
Ecclesiastic
-
Ecclesiastic
-
Computer
-
Programming
In this case, Earned Value= EV =1 MD.
This information is also known as earned value.
Earned value analysis, for the rest of us.
The method for calculating earned value.
Earned value analysis, for the rest of us- Project.
It is also used in many earned value calculations.
Preparation and Tracking Projects using Microsoft Project Earned Value.
Specify the earned value method for percent complete(optional).
But first you need to do a few things to set up earned value for reporting.
Earned value is a powerful tracking and budgeting feature in Project.
See how EVM are applied in Agile and what are the benefits:Agile Earned Value Management.
The earned value(EV) reflects the true value of the work performed.
There could be many reasons, but the point is,using a“numbers approach” with earned value will help you spot negative trends.
Use the CV(earned value cost variance) field to see the difference between the two fields.
S Curve development of a tracking project progress oreven a rigorous Earned Value analysis is the tool that should not be missed in such reports.
An earned value analysis at the end of a project really has little value. .
So this means we couldallocate extra resources in the next sprints(for the same money) in order to produce more Earned Value per sprint and to increase also the SPI.
Earned Value Management(EVM), described in PMBoK by PMI, is a technique for measuring project performance and progress in an objective manner.
Knowing what is complete and what is not complete(“%Work Completed” in ManDays), we can calculate the Earned Value(EV) of each deliverable(EV is a parameter from EVM and represents how much money values your work).
Earned value focuses on tracking the“physical” percent complete and that lends itself well to some types of projects and not so much to others.
But CPI, showing the under budget/over budget, was extremely useful for the Sponsor because he could allocate more resources,for the same money, in order to create more earned value for this project.
Earned value helps you answer questions like,“Looking at the amount of work done so far in this project, how much money were we supposed to have spent?”.
Excel Use this report to view a chart that plots AC(actual cost of work performed),planned value(budgeted cost of work scheduled), and earned value(budgeted cost of work performed) over time.
The earned value folks have a whole toolbox of possible ways to get at this kind of progress and of them all,“weighted milestones” would be my favorite.
Three key values are at the root of earned value analysis, and you pretty much need to know at least these three values to use earned value.
Earned value, variance, and performance indices over time, comparing costs and schedules to a baseline to determine if your project is on track.
Analyze project performance with earned value analysis in order to determine how much of the budget should have been spent, in view of the amount of work done so far and the baseline cost for the task, assignment, or resources.
Earned value cost variance- show the difference between how much it should have cost and how much it has actually cost to achieve the current level of completion up to the status date.
Analyze project performance with earned value analysis if you want to see how much of the budget should have been spent on tasks based on the amount of work done so far, and the baseline cost for the task, assignment, or resource.
BCWP(Earned Value or EV)(assignment field) The BCWP(budgeted cost of work performed) field contains the cumulative value of the task's, resource's, or assignments's percent complete multiplied by the timephased baseline costs.